Building a national high-speed broadband network a titanic task

Jennifer Hewett | July 16, 2008

THE Rudd Government will be preoccupied with explaining the complications of emissions trading to voters for a long time yet. But Labor will also soon have to explain the practical details of another deceptively simple "big idea" it took to the election.

Building NBN a titanic task

Broadband Minister Stephen Conroy will have his hands full getting the NBN across the line

That was the promised $4.7 billion public investment to ensure that Australia got a national high-speed broadband network. This certainly sounded good, bolstering Labor's claim to have a grip on the future in contrast to a government stuck in the past.

Putting the idea into effect is proving much, much tougher. And there is little evidence yet that Communications Minister Stephen Conroy knows how to handle the conflicting pressures he once dismissed.

It's not just the inevitable delays with the timetable for selecting a winning tender, which is now stretching into next year, it's the whole, messy argument over the rules for the ownership, running and prices of the proposed new network.

Put simply, it's Telstra versus the rest.

That power equation is hardly unusual, of course. But it's far more significant in the context of Australia having a broadband network that Labor likes to describe as crucial to the country's economic and social future.

Indeed, Conroy likens the scale and importance of creating a fibre network to the building of the Snowy Hydro project.

It's actually more like a mirage -- shimmering on the horizon, but evaporating at close range.

So far, the jargon of telecommunications talk means the vicious fighting among those supposedly turning an idea into reality has largely gone unnoticed by voters. Time will run out.

The original tender deadline was scrapped after Telstra's competitors complained they didn't have enough details of Telstra's existing network infrastructure.

Telstra argues that this is yet another tactic to try to ensure the fibre-to-the-node network is either delayed as long as possible or never actually built.

Assuming the squabbling eventually stops, the would-be bidders will have 12 weeks to consider the information before putting in their proposals.

These will be considered by the Government's expert panel for another eight weeks with a recommendation -- optimistically -- by early next year. That's just to begin what will take several years to build.

But that's also assuming that some viable agreement actually can be reached. The government's election promise is for broadband for 98 per cent of the population that has a minimum speed of at least 12 megabits per second. Given the rapidity with which technology and demand are developing, that speed will soon seem extremely slow. But it certainly beats the average broadband speeds of about 1Mbps available to a majority of the population now.

Although wireless broadband is becoming ever more popular and ever faster, it doesn't replace the need for a fibre network, particularly given that wireless slows down the more people use it. At the moment, according to Telstra's head of regulatory affairs, Tony Warren, the 3G networks are averaging around 7Mbps to 8Mbps for most people using it at home, and much less if a lot of users jump on.

Not that everyone -- even if willing to pay -- is equal in the broadband world. About a third of Australian homes are within 1.5km of an exchange. That means they can already get the higher speeds available on current networks using ADSL2+ -- more like 24Mbps than 12Mbps.

Those homes largely but not completely overlap with suburbs and residences that have cable running down their streets -- which also gives them the choice of high-speed broadband.

Add in the central business districts where a variety of companies already provide high-speed fibre networks to offices. The result is that close to 40 per cent of Australians don't need to wait for a fibre-to-the-node network to get over the politically magic 12Mbps figure. They are often well over that and rising.

The catch is the rather large problem of the rest of the country.

Although there are at least three groups proposing state-based fibre networks, the only two players proposing a national system are Telstra and Terria, the consortium led by Singtel/Optus and formerly known as G9.

The government needs a national rollout. Its contribution of $4.7 billion effectively will be a subsidy to rural areas, where the numbers of people and distances involved mean it is otherwise not economic for anyone to build.

Despite the noise made by Terria, many in the market believe that it is not a real contender, particularly given the extraordinary difficulties in raising finance and the clear reluctance of Singtel to invest its own funds in Australia. That would make Terria's primary purpose to exert sufficient pressure on the Government to drastically limit Telstra's power.

This is most easily achieved by what has become the holy grail to Telstra's competitors -- structural separation, or the splitting of the wholesale and retail services from the fibre network. It would involve Telstra hiving off the network to a completely separate company. It is complete anathema to Telstra.

And for all the talk about this option, it is not going to happen -- at least not according to the Minister, who has repeatedly and publicly ruled it out.

What is far murkier is just what the Government will end up doing on what is called operational separation. That's where the network still remains under Telstra's ownership but would be run as a stand-alone business.
Over the years, attempts by the Howard government to enforce a modest version of this on Telstra were described by Stephen Conroy while in opposition as completely inadequate and a sham.

If he tries to harden this attitude in government by toughening the rules on Telstra running a distinctly separate network, Telstra would find the idea of investing in the new network far less appealing.

It argues the current system is already absurdly expensive and inefficient.

Sol Trujillo and the boys would fight any toughening as hard as they know how. That would mean, at best, yet more delays and legal brawling.

At worst, no deal whatsoever and Labor's grand broadband plan in tattered fibres.

This is all aside from the inevitable arguments between Telstra and the newly reappointed Graeme Samuel over pricing of the new services to consumers and rivals.

It makes the Snowy Hydro look like building a backyard pool. Stephen Conroy is yet to get wet.

Your Comments:

5 Comment(s)

Vic Mooren of Melbourne 7:01pm August 20, 2008

I'm tired see all the coments, from same people working in Telstra, Optus, etc., Mr K. Rudd and Mr. Conroy, must give up, never came down, Labor Government now, my support to Technology Revolution, My Independent Coments, the people need new communications, every where waiting the Broadband truely, not the one, we have in Australia now, I call obsolete, because is not Broadband, is only all copper cables systems, and only fibre cables, between Exchange to Exchange, the new technology don't need big building, don't need repeter station every 50 kilometers, don't need maintenance, for me, it only high speed systems,low prices, and easy maintenance all ground and Submarines Stations, and in Australia, we have the best systems in the world. Came on all Australian, now we need the gold medal, but in Telecommunications.

Tony Stiller of Kureelpa 10:44am August 12, 2008

With all this infighting between telcos and who has the ministers ear at any one time, one solution would be to consolidate all telecommunications network running past everyone door into a national grid, then they could lease bandwidth to all telcos with the profits lifting bandwidth from 512Kbps to 1Gbps lifting Australia from 12th place in developed countries to rival those of Denmark and Japan etc. This would truly be a 'technology revolution', not the load of rubbish we currently hear from Mr Rudd, Senator Conroy and the telco chiefs.

Diogenies of Tweed Heads 11:02am August 06, 2008

Tony, what about the other half ? And having lived in the country (only 3 hours from Brisbane) with 3G & satellite - what a joke ! My exchange is ADSL2 enabled and according to NPAMS I can get it as I have a only 800m run of copper - but no other provider has an ADSL2 DSLAM installed. Other ISPs would put one in, but there is no affordable backhaul either - 3 guesses who the only provider of this is ? So my choice is Telstra or ADSL1 or 3G. I cry when I compare the BigPond & my current providers ADSL2 packages - Bigpond is much more expensive. Furthermore as one of the 250 ex Telstra/ex IBMGSA employees made redundant in 2003 when Telstra ofshored all its IT work I have no desire ever to use Telstra again for anything ! So what are my choices exactly ?

Tony (Telstra employee) of Canberra 4:22pm July 20, 2008

(These are my personal views, not Telstra's.) Who is going to benefit from the NBN? It sounds like half the population already has a choice of several broadband providers at high speeds. Those who don't often have competitive options with wireless broadband (Telstra, Optus, 3). Those in rural areas often have access to Next G, or they can get subsidised satellite broadband. Is it just me or does this NBN thing sound like a big waste of all our money!!

Sydney Lawrence of Manly 7:12am July 18, 2008

Stephen Conroy will have no trouble as long as he selects Telstra for the NBN build. If he doesn't it will be disaster for Australia with huge cost over-runs, long roll-out delays, horrific disruption to Australia's communications and finally the neeed for the Australian taxpayer to donate billions to complete the network build. Just as important lets be sure that we keep Australia's vital communication network with Australian ownership and under Australian control.

Story Tools

Post A Comment

We welcome your comments on this story. Comments are submitted for possible publication on the condition that they may be edited. Please provide a screen name and suburb/location - these will be published. We also require a working email address - not for publication, but for verification. Read our publication guidelines.

* Required fields

Share This Article

From here you can use the Social Web links to save Building a national high-speed broadband network a titanic task to a social bookmarking site.

Email To A Friend

* Required fields

Information provided on this page will not be used for any other purpose than to notify the recipient of the article you have chosen.

Keep up to date with all the latest Blog news, delivered straight to you.

Register now!

Sign up for a daily update of the biggest stories in IT. From Microsoft to Microformats, you'll be on top of all the latest in IT news five days a week.

Also in Australian IT

Macworld gathering without Apple

APPLE faithful are making pilgrimages to San Francisco for the start of Macworld, which is expected to miss iconic leader Steve Jobs.

Skills main mainframe issue

IN a survey of mainframe enterprise customers this year, 63 per cent ranked the skills shortage as a major concern.

Storm gives screen tappers the wobbles

THE BlackBerry Storm's wobbly touch screen gives tactile feedback to touchscreen tappers.

Steve Jobs comes clean-ish

FINALLY, finally, Steve Jobs and Apple decided to release some details about his health.

Also in the Australian

Israeli tanks enter southern Gaza city

4:00pm ISRAELI tanks rolled into Khan Yunis, the largest city in the southern Gaza Strip, just before dawn, witnesses said.

Wal King warns H1 profit to fall 60pc

THE CEO of Leighton Holdings said today first-half profit would fall 60 per cent to $100 million due to write-downs of its investme...

Windschuttle admits Quadrant 'hoax'

4:52pm QUADRANT editor Keith Windschuttle has confessed he was "tricked" into publishing an article about scares on biotechnology issues.

$10,000 off maths, science degrees

DEGREES in maths and science will be offered at discounts of more than $10,000 under changes taking effect on January 1.